Current Road Work Updates

This is a beta application. Because this application is a work in progress, there may be changes as we work on improving it.

Have questions, suggestions, or issues using the application? Let us know. 

See the map and table below for current road work and possible lane and full road closures. Some closures are intermittent or overnight. See "Notes" for more information. Additional construction projects are listed below. Visit our Smart Traffic website for live updates and traffic camera views of our roads.

Current Road work INCLUDING POSSIBLE Closures

Construction Projects - FDOT Roadways

Updated May 7th, 2019
‚Äč

Various locations along US 41, US 19 and SR 780: Construction project: Crews are installing highway lighting and constructing sidewalks at various locations along US 41, US 19 and SR 780 in Manatee and Sarasota Counties. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. Expected completion is summer 2019. The contractor is Highway Safety Devices, Inc.

 

I-275 at the Sunshine Skyway Rest Areas in Manatee and Pinellas Counties: Construction project: Improvements include constructing new rest areas and new parking lots with LED lighting, seawall repairs and extending the seawall at the Manatee County rest area to accommodate a new picnic pavilion. The Manatee County rest area is closed for renovations. Motorists should use the Pinellas County rest area during this time. The fishing piers will remain open during the closure. Construction is ongoing on the new rest area site and the seawall on the Manatee side, west of I-275. Expected completion is spring 2020. David Nelson Construction Company is the contractor. 

 

I-275 Southbound Ramp to I-75 Northbound (Exit 228): Construction project: Crews are replacing the concrete bridge deck on the southbound I-275 ramp to northbound I-75. The I-275 southbound ramp to northbound I-75 will remain closed into the summer. Traffic is being detoured north on US 41/S Tamiami Trail to SR 674/E College Avenue in Hillsborough County. A temporary traffic signal has been installed on US 41 at the southbound I-275 exit. Expect nighttime/overnight lane closures on the I-275 southbound ramp to I-75 southbound from 9 p.m. each night to 6 a.m. each morning Monday, May 6 through Friday, May 10. Expect nighttime/overnight lane closures on the I-75 northbound ramp to I-275 northbound from 9 p.m. to 6 a.m. Tuesday, May 7. Use caution and watch for changes in the traffic pattern. Expected completion is summer 2019. Cone & Graham, Inc. is the contractor.

 

 

 

I-75 at SR 70 Interchange (Exit 217): Construction project: This week, crews will work on widening I-75, the ramps, retaining and noise walls, drainage improvements, working on the bridges over SR 70 and the Braden River, and SR 70 road work.

 

  • Crews are working on the interstate bridges over the Braden River.  Boaters are urged to exercise caution if they travel underneath the bridges.  Spotters will be watching for boaters to assist them through the work zone.

     

  • Motorists should expect lane closures on I-75 during nighttime/overnight hours from  8:45 p.m. to 6 a.m. (northbound) or 8 p.m. to 5 a.m. (southbound) through the duration of the construction.

     

  • Motorists should expect lane closures on SR 70 during nighttime/overnight hours from 8 p.m. to 5 a.m. through the duration of the construction.

     

  • Motorists should expect lane shifts on I-75 and SR 70 through the duration of the construction.

     

  • Drivers should exercise caution and be aware of construction vehicles entering and exiting the interstate through the duration of the construction.

 

Variable message signs will be in place to alert drivers that work is underway. Estimated completion is late 2021. The contractor is Sacyr Construction USA., LL

C.

I-75 at the University Parkway Interchange (Exit 213): Construction project: Crews are installing landscaping and irrigation systems at the I-75 and University Parkway interchange. Lane closures on I-75, if needed, will occur between 8 p.m. and 5 a.m. Lane closures on University Parkway, if needed, will occur between 9 p.m. and 6 a.m. Estimated completion is spring 2019. The contractor is Frankie Valdez Company, Inc.

 

US 41 from 301 Boulevard to 21st Avenue: Construction project: Crews are installing concrete traffic separators/directional turn-lanes within the median, resurfacing the roadway, improving drainage, and installing new signing and pavement markings. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from      9 a.m. to 4 p.m. (not within 600 feet of a signalized intersection). The northbound outside lane will be closed from 32nd Avenue to 30th Avenue for approximately two weeks while crews complete drainage work. Expected completion is summer 2019. Blacktip Services Incorporated is the contractor.

 

SR 64 at Rye Road: Construction project: Crews are constructing a multi-lane roundabout; resurfacing the roadway; improving drainage, and installing new highway lighting and landscaping. A traffic switch has been implemented shifting traffic to the current westbound lanes using temporary crossovers. Traffic will be reduced to one lane in each direction throughout the project limits. Rye Road will remain accessible during this time. The speed limit on State Road 64 will be reduced to 45 mph. IBT Construction is the contractor. Expected completion is late 2019.