Current Road Work Updates

This is a beta application. Because this application is a work in progress, there may be changes as we work on improving it.

Have questions, suggestions, or issues using the application? Let us know. 

See the map and table below for current road work with possible lane and full road closures. Some closures are intermittent or overnight. See "Notes" for more information. Additional construction projects are listed below for FDOT (State) roadways. Visit our Smart Traffic website for live updates and traffic camera views of our roads.

Current Road work INCLUDING POSSIBLE Closures

Construction Projects - FDOT Roadways

Updated December 6th, 2019

Various locations along SR 684 and US 301: Construction project: Crews are installing new highway lighting at various locations along SR 684 from Gulf Drive to 9th Street W and on US 301 from Tallevast Road to 9th Street E. Expect nighttime/overnight lane closures from 10:30 p.m. to 6 a.m. Expected completion is early 2020. PowerCore, Inc. is the contractor.

 

I-275 at the Sunshine Skyway Rest Areas in Manatee and Pinellas Counties: Construction project: Improvements include constructing new rest areas and new parking lots with LED lighting, seawall repairs and extending the seawall at the Manatee County rest area to accommodate a new picnic pavilion.  The Manatee County rest area is closed for renovations. Motorists should use the Pinellas County rest area during this time. The fishing pier will remain open during the closure; however, there will be intermittent flagging operations along the fishing pier access road in Manatee County for moving of equipment and materials. Expected completion is spring 2020. David Nelson Construction Company is the contractor. 

 

I-275 Southbound Ramp to I-75 Northbound (Exit 228): Construction project: Crews are replacing the concrete bridge deck on the southbound I-275 ramp to northbound  I-75. The I-275 southbound ramp to northbound I-75 will remain closed through late November. Traffic is being detoured north on US 41/S Tamiami Trail to SR 674/E College Avenue in Hillsborough County. A temporary traffic signal has been installed on US 41 at the southbound I-275 exit. Expect nighttime/overnight lane closures on the I-275 southbound ramp to I-75 southbound from 9 p.m. each night to 6 a.m. each morning through Wednesday, November 27. Expect nighttime/overnight lane closures on I-75 northbound and I-75 southbound between Moccasin Wallow Road and just south of the I-275 interchange from 9 p.m. each night to 6 a.m. each morning through Wednesday, November 27. Use caution and watch for changes in the traffic pattern. Expected completion is spring 2020. Cone & Graham, Inc. is the contractor.

 

I-75 at SR 70 Interchange (Exit 217):  Construction project: This week, crews will work on widening I-75, the ramps, retaining walls, noise walls, excavating interchange and SR 70 stormwater ponds and drainage, and working on the bridges over SR 70 and the Braden River.

 

  • Motorists should expect lane closures on I-75 during nighttime/overnight hours from 8:45 p.m. to 6 a.m. (northbound) or 8 p.m. to 5 a.m. (southbound) through the duration of the construction.
  • Motorists should expect lane closures on SR 70 during nighttime/overnight hours from 8 p.m. to 5 a.m. through the duration of the construction.
  • Motorists should expect lane shifts on I-75 and SR 70 through the duration of the construction.
  • Drivers should exercise caution and be aware of construction vehicles entering and exiting the interstate through the duration of the construction.

 

Variable message signs will be in place to alert drivers that work is underway. Estimated completion is late 2021. The contractor is Sacyr Construction USA, LLC.

 

US 301 (State Road 43) from 2nd Avenue to 51st Avenue: Construction project: Crews are resurfacing the roadway; improving drainage; installing guardrail and highway lighting, and improving the railroad crossing. Expect nighttime/overnight lane closures from 9 p.m. to 5:30 a.m. and possible daytime lane closures from 9 a.m. to 4 p.m. during construction. Superior Asphalt, Inc. is the contractor. Expected completion is summer 2020.

 

US 301 (State Road 43) from Moccasin Wallow Road to the Hillsborough County Line: Construction project: Watch for daytime shoulder closures as crews install project signs, erosion control devices and begin milling and paving operations. The improvements under this contract consist of milling and resurfacing, super elevation correction, shoulder reconstruction, turnout construction, drainage improvements, shoulder treatment, signing and pavement markings.

 

SR 789 at the Longboat Key Pass Bridge: Construction project: Crews are making structural, electrical and mechanical repairs on the bridge. Expect nighttime/overnight lane closures from 9 p.m. to 6 a.m. Sidewalk closures are also expected during construction. Southern Road & Bridge, LLC is the contractor. Expected completion is fall 2019.

 

 

SR 64 at Rye Road: Construction project: Crews are constructing a multi-lane roundabout; resurfacing the roadway; improving drainage, and installing new highway lighting and landscaping. Traffic has been shifted to the southside of SR 64 with one 10 foot lane in each direction. The speed limit on State Road 64 has been reduced to 25 mph within the construction zone. Motorists should expect daytime and nighttime flagging operations at the intersection of SR 64 and Rye Road through Friday, November 8 while crews are working. IBT Construction is the contractor. Expected completion is late 2019/early 2020