www.mymanatee.org
Manatee County Government Administrative Center Commission Chambers, First Floor 9:00 a.m. - September 27, 2016
REVISED September 27, 2016 - Regular Meeting
Agenda Item #29


Subject
Utility Work Agreement

Briefings
Briefing Provided Upon Request

Contact and/or Presenter Information

Sia Mollanazar, PE, Deputy Director - Engineering Services



Action Requested

Adoption of Resolution R-16-148 and authorization for the Chairperson to execute a Utility Work Agreement with the Florida Department of Transportation (FDOT) for the relocation of  ITS Conduit.



Enabling/Regulating Authority

State Statute: 337.403 Requires the County to take action at its own expense to move its utilities upon demand from the FDOT.



Background Discussion

The FDOT is currently engaging in a project which involves constructing, reconstructing, or otherwise changing a public road identified as I-75 and SR 64.  The project requires the location, protection, relocation, installation, adjustment, or removal of ITS Conduit.

  • Design work shall be completed by County staff or consultant.
  • The FDOT agrees to reimburse County up to $155,642 for construction.
  • Manatee County will provide the final engineering design, plans, technical special provisions, and a cost estimate prior to bid phase.


County Attorney Review
Formal Written Review (Opinion memo must be attached)

Explanation of Other


Reviewing Attorney
D'Agostino

Instructions to Board Records

Please return four (4) signed originals of the Utility Work Agreement and (2) certified copies of the Resolution. to Barbara Green, Public Works Department, extension 7355.



Cost and Funds Source Account Number and Name
$155,642.00 Acct. Key: 001-0004900

Amount and Frequency of Recurring Costs
N/A


Attachment:  201032-6-56-13 MCIT UWA_(ITS).pdf
Attachment:  Resolution_2016.pdf
Attachment:  Response to CAO Matter No. 2016-0669.pdf