www.mymanatee.org
Manatee County Government Administrative Center First Floor, Chambers 9:00 a.m. - October 5, 2017
REVISED October 5, 2017 Land Use Meeting
Agenda Item #12


Subject
PDMU-16-16(Z)(G) - FLM, Inc.,/Parrish Lakes - DTS20100092 - MEPS605 - Quasi-Judicial - Stephanie Moreland, Principal Planner

Briefings
Briefing Provided Upon Request

Contact and/or Presenter Information

Presenter:    

   Stephanie Moreland, Principal Planner, 941-748-4501 ext. 3880

Contact:

   Bobbi Roy, Planning Coordinator, 941-748-4501 ext. 6878



Action Requested

RECOMMENDED MOTION:

Based upon the staff report, evidence presented, comments made at the Public Hearing, and finding the request to be CONSISTENT with the Manatee County Comprehensive Plan, the action of the Planning Commission, and the Manatee County Land Development Code, as conditioned herein, and making a determination that the proposed buildings exceeding 35 feet in height are consistent with Land Development Code (LDC) Section 402.7.D.9, I move to ADOPT Manatee County Zoning Ordinance No. PDMU-16-16(Z)(G); APPROVE the General Development Plan with Stipulations; GRANT Special Approval for a project: 1) in the MU FLUC; 2) adjacent to a perennial stream; 3) partially in the 25 year floodplain;  ADOPT the Findings for Specific Approval and GRANT Specific Approval for an alternative to LDC Section 403.12.D.3(k)[reduction of rear yard setbacks for accessory structures in NC Overlay District], as recommended by the Planning Commission.

(Commissioner Trace)



Enabling/Regulating Authority

Manatee County Comprehensive Plan

Manatee County Land Development Code



Background Discussion

• FLM, Inc., applicant for Parrish Lakes requests approval of a Development of Regional Impact (DRI) to allow a two phased mixed-use development  to include 3,300 residential units; 400,000 square feet of retail space and 50,000 square feet of office space.

• The 1,155± acre site is on the south side of Moccasin Wallow Road, approximately 0.74 miles east of I-75, and north side of Erie Road in northern Manatee County approximately three (3) miles south of the Hillsborough County line. 

• Historically, the site was used for agricultural uses. 

• A 330-foot wide Florida Power and Light transmission line easement runs across the eastern part of the site extending from north to south. 

• The Buffalo Canal traverses the site from east to west, near the center of the site.  Special Approval is required for a project adjacent to a perennial stream.
• The 2020 Manatee County Comprehensive Plan designates the site as MU (Mixed Use).  The 330-foot wide FPL Easement is designated as P/SP-1(Public/Semi-Public-1) on the Future Land Use Map.

• The site is currently zoned A (General Agriculture- one dwelling unit per five acres) and A-1(Suburban Agriculture-one dwelling unit per one acre).  The site is partially in the NC (North County Overlay District).

• The proposed densities (3.0) dwelling units per acre) and intensities (F.A.R. 0.22) are consistent with the maximum potential density and intensity allowed for the MU (nine dwelling units per acre), and P/SP-1 (zero dwelling units allowed) FLUCs.

• The General Development Plan shows Carter Road dissects the site from Moccasin Wallow Road to the north to Erie Road to the south.  Sawgrass Road runs in a northerly to southerly direction connecting a future right-of-way to the north and Erie Road to the south. There are three access points connecting Moccasin Wallow Road, eight access points connecting Carter Road, six access points connecting Sawgrass Road and one access connecting Erie Road.

• There are13.0± acres of wetlands on-site, of which 0.40± acres will be impacted due to the proposed alignment of Sawgrass Road. 

• There are 26± acres proposed for recreational amenities to include community open space/park and private recreational facilities.  

• Staff recommends approval subject to the recommended stipulations.

• On July 13, 2017, by a vote of 7 – 0, the Planning Commission continued the public hearing to August 10, 2017. On August 10, 2017, by a vote of 5 – 0, the Planning Commission recommended approval. Mr. Rahn and Mr. Rutledge were absent.

• On August 3, 2017, by a vote of 6 – 0, the Board of County Commissioners continued the public hearing to September 7, 2017. Commissioner Smith was absent. On September 7, 2017, by a vote of 6 – 0, the Board of County Commissioners continued the public hearing to October 5, 2017. Commissioner Benac was absent.

• A summary of the public comments heard at the August 10, 2017 Planning Commission and September 7, 2017 Board of County Commissioners public hearings is in the staff report attached to this memo. 



County Attorney Review
Other (Requires explanation in field below)

Explanation of Other
Sarah Schenk reviewed and responded by email to Matter 2017-0381 on July 11, 2017.

Reviewing Attorney
Schenk

Instructions to Board Records
Please forward a copy of the executed document and Letter from the Florida Department of State to bobbi.roy@mymanatee.org.

Cost and Funds Source Account Number and Name
N/A

Amount and Frequency of Recurring Costs
N/A


Attachment:  Parrish Lakes staff report for Rezone and GDP for 100517BCC .pdf
Attachment:  2 - Maps and Aerials - Parrish Lakes GDP - PDMU-16-16(Z)(G) - 100517 BCC.pdf
Attachment:  3 - General Development Plan - Parrish Lakes PDMU-16-16(Z)(G) 100517 BCC.pdf
Attachment:  4 - Zoning Disclosure Affidavit - Parrish Lakes GDP 100517 BCC.pdf
Attachment:  5 - Newspaper Advertising - Parrish Lakes GDP 100517 BCC.pdf
Attachment:  6 - Parrish Lakes Zoning Ordianance 100517 BCC.pdf
Attachment:  Update Memo PDMU-16-16 BCC 10052017.pdf
Attachment:  Letter from Applicant on Presentation time.pdf
Attachment:  Revised Ordinance from update memo Parrish Lakes Zoning Ordianance 100517.pdf