Agenda Item #29


Subject
Change Order No. Three (3) to Work Assignment 54 - Lake Manatee Dam Phase II Repairs, Master Agreement 11-1569BG Utilities Engineer of Record

Briefings
None

Contact and/or Presenter Information
Contact:
Abigail Jenkins, Contracts Negotiator, Procurement Division, Financial Management Department, x3062

Presenters:
Jeff Streitmatter, Project Management Division Manager, Public Works Department, x7335
Anthony Russo, Project Management Division Manager, Public Works Department, x7349
Mark Simpson, Water Division Manager, Utilities Department, x5258

Action Requested
Authorization for County Administrator or his designee to execute Change Order No Three (3) to Work Assignment 54, Master Agreement 11-1569BG with Carollo Engineers, Inc., in the amount of $1,660,884.00 for a revised total amount of $2,877,206.00.

Enabling/Regulating Authority
Manatee County Code of Laws

Background Discussion

Change Order Three (3) to Work Assignment 54, Master Agreement 11-1569BG, will provide additional field investigations, design, and constructions services for the construction of a supplemental cutoff wall, replacements approach walls, and repairs to the downstream stilling basin and discharge apron at the lake Manatee Dam service spillway.

Procurement History

On November 8, 2017, the Board of County Commissioners approved the Master Agreement 11-1569BG with Carollo Engineers, Inc. of Sarasota, FL to provide Utilities Engineer of Record services. This Master Agreement was established for the purpose of conducting studies and preparing reports regarding maintenance and operation of existing facilities, systems, and connections; performing rate studies and providing technical assistance on all utility issues, operational, technical, engineering, and financial issues, including but not limited to bond refinancing, grant funding, loans, and bond issues related to utility systems.

On July 27, 2015, the County approved Work Assignment 54 to provide preliminary investigation and design services associated with Phase II repairs to the Lake Manatee Dam and its appurtenant structures for a total cost of $570,012.00.

On October 20, 2015, the County approved Change Order No. One (1) to Work Assignment 54 to install four (4) additional piezometers to monitor the pumping tests associated with the Phase II repair preliminary design. The potential need for the additional piezometers was identified in the Consultant's original Scope of Services Phase and was confirmed during hydrogeological modeling at existing wells during Phase II repair preliminary design field investigations increasing the total amount by $30,316.00 for a revised total amount of $600,328.00.

On April 4, 2017, the County approved Change Order No. Two (2) to Work Assignment 54 Master Agreement 11-1569BG to conduct additional field investigations, perform additional engineering analysis, prepare 90% and final design documents, provide permitting services, and provide bidding phase services and construction phase services increasing the total amount by $615,994.00 for a revised cost of $1,216,322.00.



County Attorney Review
Not Reviewed (No apparent legal issues)

Explanation of Other


Reviewing Attorney
N/A

Instructions to Board Records
Original to Board Records.

Email copies of Change Order to:
Carollo Engineers, Inc. - Robert Cushing (rcushing@carollo.com)
Public Works Department -Anthony Russo (anthony.russo@mymanatee.org)
Procurement Division - Abigail Jenkins (Abigail.jenkins@mymanatee.org)

Cost and Funds Source Account Number and Name
1,660,884.00/404-6026075 - Utility Rates

Amount and Frequency of Recurring Costs
N/A