Agenda Item #26


Subject
Change Order 1 to Agreement 14-0846OV, Southwest Water Reclamation Facility (SWWRF) Nitrogen Removal

Briefings
None

Contact and/or Presenter Information

Contact:
Olga Valcich, Purchasing Division, Financial Management Department,  Ext. 3055

Presenter / Information:
Anthony Benitez, Project Management Division, Public Works Department, Ext. 7333
Jeff Streitmatter, Project Management Division, Public Works Department, Ext. 7335



Action Requested

Authorize the County Administrator or his designee to execute Change Order 1 to Agreement T1400056 with Vogel Bros. Building Co., decreasing the total contract sum by $200,013.93 and adding 196 calendar days to the final completion schedule.



Enabling/Regulating Authority

Manatee County Code of Laws



Background Discussion

Change Order 1 reduces the Agreement  by $200,013.93 from $12,782,000.00 to $12,581,986.07.

The changes provide the following:

  • Installation of steel pipe in lieu of ductile iron piping at splitter 1.
  • Modification to the NRCY (Nitrified Recycle) pump discharge header elevation above the aeration basin walls in lieu of drilling through existing walls between aeration basins.
  • Changing stainless steel blower piping from specified seamless material to welded piping material.
  • Abandonment of embedded rails in anoxic basins.
  • Aeration basin construction sequence change.

The benefits created by these modifications include cost savings to the County through providing for an equivalent quality end product and allowing for safe installation methods.  This change enables plant staff to operate the facility with less impact of potential spills during seasonal high flows.

This change requires adding 196 calendar days to the schedule, which changes the final completion date from April 29, 2016, to November 11, 2016.

On November 6, 2014, the BCC executed an Agreement with Vogel Bros. Building Co., Lakeland, FL, in the amount of $12,782,000.00.



County Attorney Review
Not Reviewed (No apparent legal issues)

Explanation of Other


Reviewing Attorney
N/A

Instructions to Board Records

Original to Board Records

Copy of executed Agreement emailed to:
bbocchino@vogelbldg.com
Anthony.Benitez@mymanatee.org
Kathleen.Casey@mymanatee.org
Olga.Valcich@mymanatee.org
Jeff.Goodwin@mymanatee.org



Cost and Funds Source Account Number and Name
Funding Source: 4046079080-534000-6079080-0004, Utility Rates

Amount and Frequency of Recurring Costs
N/A


Attachment:  CO.1_Nitrogen Removal_T.1400045.NITROGEN.CO_1.VOGEL BROS.BUILDING..pdf