Lennar Homes / Heritage Harbour Ph II Credit Authorization and Final Authorization of Credit CA-14-04(T)

Briefings
None

Contact and/or Presenter Information
Sharla Fouquet
Impact Fee Program Manager
748-4501, Extension 3966

Action Requested
Authorization for Chairman to execute Credit Authorization CA-14-04 (T) for payment in lieu of construction of the Port Harbour Parkway Extension, per Amended and Restated Local Development Agreement executed on September 14, 2014, between Lennar Homes, LLC, Manatee Land Investors, LLC, Upper Manatee 288 LLC, and Manatee County. 

Authorization for Chairman to execute Final Authorization of Road Impact Fee Credit in the total amount of $2,149,201.78 per Credit Authorization CA-14-04 (T).




Enabling/Regulating Authority
Manatee County Comprehensive Plan
5.1 Traffic Circulation Element
Future Major Roadways

Land Development Code
Chapter 8 - Impact Fees
Section 807 - Credits

Background Discussion
Chapter 8, Section 807, of the Manatee County Land Development Code provides for authorization by the Board of County Commissioners for Impact Fee Credits for contributions, payments, construction, or dedications made to Manatee County against applicable components of impact fees.  

Under the terms of amended and restated Land Development Agreement 08-08 for Heritage Harbour (said amendment/restatement having been executed by Lennar Homes, Manatee Land Investors, LLC, Upper Manatee 288 LLC, and Manatee County on September 14, 2014), Lennar Homes was required to pay to Manatee County the sum of $2,299,201.78 for the extension of Port Harbour Parkway.  The amended Land Development Agreement further stipulated that Lennar would immediately receive road impact fee credits in exchange for this payment, less $150,000.00 (LDA Article II, Section 2.1., Paragraph D.).    

Lennar Homes wired a $2,299,201.78 payment to Manatee County on December 17, 2014.  Lennar is, therefore, now entitled to road impact fee credits in the amount of $2,149,201.78.  They may use these credits in the Heritage Harbour development for road impact fees on any permits applied for on or after December 21, 2011.

County Attorney Review
Not Reviewed (Utilizes exact document or procedure approved within the last 18 months)

Explanation of Other


Reviewing Attorney
N/A

Instructions to Board Records
Please send original executed documents to Sharla Fouquet, Financial Management Department (County Administration Building, Suite 939)

Cost and Funds Source Account Number and Name
N/A

Amount and Frequency of Recurring Costs
N/A


Attachment:  Credit Auth CA-14-04 (T) - Lennar Homes - Heritage Harbour Ph II.pdf
Attachment:  Final Auth of Cr CA-14-04 (T) - Lennar Homes - Heritage Harbour Ph II.pdf
Attachment:  Wire Transfer Confirm from Finance.pdf