Agenda Item #37


Subject
Long Bar Pointe Drainage Facility Relocation Agreement

Briefings
Briefing Provided Upon Request

Contact and/or Presenter Information

Thomas Gerstenberger, P.E., Stormwater Engineering Division Manager (Ext. 7228)



Action Requested

Authorization for the Chairman to execute Long Bar Pointe Drainage Facility Relocation Agreement with Cargor Partners VIII, Long Bar Pointe, LLLP (Developer) to relocate existing County owned and maintained stormwater retention facility and incorporate into proposed stormwater management system for the proposed Long Bar Pointe, Phase 1, Parcels C & B2 planned development project.



Enabling/Regulating Authority

Florida Statute, Chapter 125, Section 125.01-Powers and Duties



Background Discussion
  • The County constructed drainage facilities (retention ponds) along the Right-of-Way of El Conquistador Parkway to manage stormwater runoff.
  • The County is presently responsible for maintenance and re-certification of these drainage facilities.  These existing drainage facilities are included in a recorded Drainage/Stormwater Easement (O.R. Book 2374, Pages 3755-3765).
  • The Developer is proposing a Planned Development Residential project consisting of 200 dwelling units.  These site improvements affect the location of one of the existing County maintained drainage facilities.
  • The Developer, in coordination with staff, has crafted the subject Agreement to relocate the County drainage facility into a proposed onsite retention pond including associated conveyance and outfall systems.
  • The Developer is responsible for the cost associated with design, permitting, and construction of the relocated stormwater facility, conveyance systems, and outfall systems.  In addition, the Developer is not seeking impact fee credits for the stormwater facility relocation.
  • Maintenance of the proposed relocated drainage facilities including retention ponds, conveyance, and outfall system will be the responsibility of the Developer or their designees.  The existing Drainage/Stormwater Easement referenced above would be vacated.
  • The County would accept a Public Flowage Easement to maintain the free flow of drainage runoff from El Conquistador Parkway should the Developer or their designees fail to maintain the proposed drainage facilities in functioning order.

All costs associated with design, permitting, and construction of the relocated stormwater facility and conveyance/outfall systems shall be borne by the Developer.  In addition, the Developer is not seeking impact fee credits for the stormwater facility relocation.



County Attorney Review
Other (Requires explanation in field below)

Explanation of Other

This Agreement has been reviewed and coordinated through the County Attorney’s Office, Public Works Department, and the Developer.



Reviewing Attorney
Clague

Instructions to Board Records

Please return one copy of the original, signed Agreement to the Public Works Department, attention Thomas Gerstenberger, P.E., Stormwater Engineering Division Manager.  A separate original, signed copy shall be available for pick-up by the Developer.



Cost and Funds Source Account Number and Name
N/A

Amount and Frequency of Recurring Costs
N/A


Attachment:  OR 2347 PG 3755.pdf
Attachment:  El Con Pkwy Pond Relocation (01-15-14).pdf
Attachment:  LBP Drainage Facility Relocation Agreement (CAO Comments).pdf
Attachment:  LBP Drainage Facility Relocation Agreement - Final (executed).pdf
Attachment:  LBP Drainage Facility Relocation Agreement - Public Comment Letter.pdf