www.mymanatee.org
Manatee County Government Administrative Center Commission Chambers, First Floor 9:00 a.m. - August 27, 2013
REVISED August 27, 2013 - Regular Meeting
Agenda Item #26


Subject
LAP Agreement with FDOT Traffic Signal Update at CR789 (Gulf Dr) and Marina Drive

Briefings
None

Contact and/or Presenter Information

Eyra Cash, Project Engineer II, Ext 7344

Jeff Streitmatter, Project Management Division Manager, Ext 7335



Action Requested
Adoption of Resolution R-13-152, authorizing the chairman to execute a Local Agency Program (LAP) agreement with the Florida Department of Transportation (FDOT) for a mast arm traffic signal upgrade at CR 789 (Gulf Dr.) and Marina Dr. intersection.

Enabling/Regulating Authority
Florida Statutes, Section 339.12

Background Discussion
  • Project construction will replace and upgrade the existing span wire signalization with mast arm signalization.
  • Manatee County is responsible for project management services for the signal upgrade, and is responsible to fund the design services element of the project.  FDOT is participating by providing funds for construction and CEI (construction, engineering, and inspection) service elements.
  • Funds of $134,370 are programmed in FDOT's FY13/14 work program.  Execution of Resolution R-13-152 and Local Agency Program agreement are required to memorialize the funding designation and provide the method for reimbursement.


County Attorney Review
Not Reviewed (Utilizes exact document or procedure approved within the last 18 months)

Explanation of Other


Reviewing Attorney
N/A

Instructions to Board Records
Return three original signature LAP agreements and two certified copies of the Resolution to Barbara Green, Public Works, for transmittal to FDOT.

Cost and Funds Source Account Number and Name
341-6084660 Local Option Gas Taxes

Amount and Frequency of Recurring Costs
$134,370.00


Attachment:  431020-1_ LAP Agreement.pdf
Attachment:  R-13-152_Resolution.pdf