www.mymanatee.org
Manatee County Government Administrative Building First Floor, Chambers August 11, 2016 - 9:00 a.m.
REVISED August 11, 2016 - Planning Commission
Agenda Item #4


Subject
PDUI-16-05(G) - Tropicana Manufacturing Company, Inc./Tropicana Master Development Plan - DTS20160154 - MEPS546 - Quasi-Judicial - Rossina Leider

Briefings
None

Contact and/or Presenter Information

Presenter:

   Rossina Leider, Planner, 941-748-4501 ext. 6859

Contact:

   Bobbi Roy, Planning Coordinator, 941-748-4501 ext. 6878



Action Requested

RECOMMENDED MOTION:

Based upon the staff report, evidence presented, comments made at the Public Hearing, and finding the request to be CONSISTENT with the Manatee County Comprehensive Plan and the Manatee County Land Development Code, as conditioned herein, I move to recommend APPROVAL of Manatee County Zoning Ordinance No. PDUI-16-05(G); APPROVAL of the Master Development Plan with Stipulations A.1 – A.5, B.1, and C.1 – C.2, as recommended by staff.

 



Enabling/Regulating Authority

Manatee County Comprehensive Plan

Manatee County Land Development Code



Background Discussion

• Mr. Alan Prather, Esq, with Porges, Hamlin, Knowles, & Prouty, P.A, agent for the property owner, is requesting approval of a Master Development Plan (MDP) for the Tropicana Manufacturing Company pursuant the Manufacturing Development Program (LDC Section 357).

• The Master Development Plan proposes a total of 4,000,000 square feet of manufacturing and accessory uses (including  the existing 2,243,858 square feet facility) on a ±175.94–acre site generally located north of US 301, east of 9th Street East, west of 15th Street East, and south of 13th Avenue East.

• The Tropicana site is designated under the IU (Industrial Urban) Future Land Use Category (FLUC), zoned PDUI (Planned Development Urban Industrial), and part of the MDO (Manufacturing Development Overlay District).

• The proposed Master Development Plan is consistent with the requirements of the approval process set forth in LDC Section 357.6., which includes the following:


   - Attend a Pre-conference meeting with County staff. The Pre-Conference meeting was held on 12/18/2015.
   - Apply for a Master Development Plan Certification of Eligibility (MDPCE). Manatee County issued the MDPCE on 02/18/2016. 
   - Submit an application for approval of a MDP using an existing planned development and site plan approved in accordance with Chapter 3 Part IV (Site Plan Review) meeting the requirements of LDC Section 357.

•  The proposed MDP is substantially consistent with:

      -   The General Development Plan for Tropicana Products, Inc. [PDUI-02-27(Z)(G)] approved by the Board of County Commissioners on 11/02/2004, and
  
      - The Preliminary/Final Site Plan (Master Plan) for Tropicana Manufacturing Company, Inc. [PDUI-12-01(P)/FSP-12-34] administratively approved on 01/15/2013. The MDP identifies the same permitted uses, amount of maximum allowable square footage, dimensional criteria (setbacks, buildings height, buffers, open space), parking, utilities and stormwater facilities.

 • The MDP identifies a list of “Permitted Uses” (limited to manufacturing uses, and accessory uses incidental to manufacturing activities), proposes a maximum FAR of 0.52 (1.25 is allowed within the IU zoning district), and 13.79% of open space (minimum 10% is required). 

• The proposed MDP is consistent with the provisions of the Comprehensive Plan,  fulfilling the regulations of LDC Section 402.17 – PDUI Zoning District, and complies with all the requirements of LDC 357.6.6 related to the “Criteria for approval of a Master Development Plan”.

• Staff recommends approval.



County Attorney Review
Other (Requires explanation in field below)

Explanation of Other
Sarah Schenk reviewed and responded by email.

Reviewing Attorney
Schenk

Instructions to Board Records
N/A

Cost and Funds Source Account Number and Name
N/A

Amount and Frequency of Recurring Costs
N/A


Attachment:  Staff Report - Tropicana - PDUI-16-05(G).pdf
Attachment:  Attachment 2 - Maps.pdf
Attachment:  Attachment 3 - Certification of Eligibility.pdf
Attachment:  Attachment 4 - Master Development Plan.pdf
Attachment:  Attachment 5 - Extension Letters.pdf
Attachment:  Attachment 6 - Copy of Newspaper Advertising.pdf