www.mymanatee.org
Manatee County Government Administrative Center First Floor, Commission Chambers 10:00 a.m. - April 22, 2014
REVISED April 22, 2014 - Regular Meeting
Agenda Item #29


Subject
Bonds - Concession, Phase II, Block B, and Phase III - Release Private Improvements Agreement, Release Letter of Credit

Briefings
None

Contact and/or Presenter Information

Carmen Mosley, Sr. Fiscal Services Manager, 708-7450, Ext. 7209

Jane Oliver, Fiscal Analyst, 708-7450, Ext 7613



Action Requested
  • Release Required Improvements Agreement and Temporary Construction Easement for Private Improvements – Final Lift of Asphalt;
  • Release Letter of Credit No. 388168861 and any associated amendments in the Amount of $163,309.59


Enabling/Regulating Authority
N/A

Background Discussion

On April 23, 2013, the Board of County Commissioners accepted a Private Improvements Agreement (Performance) to ensure the roadways would be completed for this project.  On March 17, 2014, the developer passed the final lift of asphalt inspection.  The developer has completed all the required private improvements secured by this Agreement and security which were required by Manatee County in order to release this.



County Attorney Review
Not Reviewed (No apparent legal issues)

Explanation of Other


Reviewing Attorney
N/A

Instructions to Board Records
N/A

Cost and Funds Source Account Number and Name
N/A

Amount and Frequency of Recurring Costs
N/A