www.mymanatee.org
Manatee County Government Administrative Center Manatee Room, Fourth Floor 1:30 p.m. - November 14, 2017
November 14, 2017 - Work Session
Agenda Item #1


Subject
Lake Manatee Dam Phase 2 Repair Update

Briefings
None

Contact and/or Presenter Information
Mark Simpson, Water Division Manager, x-5258

Action Requested
Status update provided for Board information and preparation for upcoming needed Board approvals.

Enabling/Regulating Authority
The Utilities Department operates and maintains the Lake Manatee Dam.

Background Discussion
The Phase 1 repair of the Lake Manatee Dam was completed in 2014. Phase 2 repairs, primarily envisioned as downstream rehabilitation, were expected to occur in 2016 following a typical design, bid, and build process. During the repair design, site investigations indicated the need for additional work on the upstream portion of the dam in the area of the primary spillway. Information presented in this work session will brief the Board on the needed rehabilitation, the options being evaluated, and the expected schedule.

County Attorney Review
Not Reviewed (No apparent legal issues)

Explanation of Other


Reviewing Attorney
N/A

Instructions to Board Records
None


Cost and Funds Source Account Number and Name
Utilities Rates/Reserves

Amount and Frequency of Recurring Costs
Annual Dam Inspections - $60,000


Attachment:  2017 Phase 2 BCC work session.pdf