Manatee County Government Administrative Center Commission Chambers, First Floor 9:00 a.m. - March 12, 2013
March 12, 2013 - Regular Meeting
Agenda Item #27


Subject
Coquina Beach Turnaround West of State Road 789

Briefings
None

Contact and/or Presenter Information

Brian Martineau, Sr. Engineering Specialist, ext. 7243

Jeff Streitmatter, Project Management Division Manager, ext. 7335



Action Requested

Adoption of Resolution R-13-046, authorizing the Chairman to execute a Local Agency Program (LAP) Agreement with the Florida Department of Transportation (FDOT) for upgrading an existing bus/trolley turnaround at Coquina Beach Turnaround West of SR 789.  (FPN: 429869-1-58/68-01).



Enabling/Regulating Authority

Florida Statute ยง339.12



Background Discussion
  • Manatee County and the Florida Department of Transportation (FDOT) are participating in the upgrade of an existing bus/trolley turnaround at Coquina Beach from the existing shell surface to a pervious asphalt surface and reinstalling the bollards.
  • Manatee County is responsible for project management services for the upgrade, and is responsible for funding the design services of the project.  FDOT is participating by providing the funding for the construction services, and construction, engineering, and inspection (CEI) service element of the project.
  • Funds of $289,486.00 are programmed in FDOT's work program for the FY 12/13 for the construction and CEI elements of the project.  Execution of R-13-046 and the Local Agency Program (LAP) Agreement are required to memorialize the funding designation and provide the method for reimbursement of construction and CEI costs.


County Attorney Review
Not Reviewed (No apparent legal issues)

Explanation of Other


Reviewing Attorney
N/A

Instructions to Board Records
Return two certified copies of the Resolution and three original LAP Agreements to Carmen Mosley, Public Works, ext. 7209, for transmittal to FDOT.

Cost and Funds Source Account Number and Name
436-6084160 Transit System Capital Improvement

Amount and Frequency of Recurring Costs
$289,486.00