Manatee County Government Administrative Center Commission Chambers, First Floor 9:00 a.m. - August 22, 2017
August 22, 2017 - Regular Meeting
Agenda Item #17


Subject
Change Order 3 to Agreement 14-3257CD: Fort Hamer Bridge Project with Road Improvements on Fort Hamer Road and Upper Manatee River Road

Briefings
None

Contact and/or Presenter Information

Contact: Chris Daley, Financial Management Department, Procurement Division, Ext. 3048.

Presenters: Michael Sturm, Engineer II, Ext. 7332, and Jeff Streitmatter, Public Works Department, Project Management Division, Ext 7335.



Action Requested

Authorize the County Administrator or his designee to execute Change Order 3 to Agreement 14-3257CD: Fort Hamer Bridge Project with Road Improvements on Fort Hamer Road and Upper Manatee River Road with Johnson Bros. Corporation, a Southland Company, Lithia, FL, adding 140 calendar days to the construction schedule with no additional increase to the Agreement.



Enabling/Regulating Authority

Manatee County Code of Laws



Background Discussion

Change Order 3 provides for an additional 140 calendar days for the traffic signalization work associated with Change Order 1 at no additional cost to the Agreement.

PROCUREMENT BACKGROUND

At its meeting on February 26, 2015, the Board of County Commissioners executed Agreement 14-3257CD with Johnson Bros. Corporation, a Southland Company, LLC, in the amount of $32,690,155.48 based on a completion time of 630 calendar days for the construction of a bridge over the Manatee River connecting Upper Manatee River Road to Fort Hamer Road along with roadway functional improvements to both Upper Manatee River Road and Fort Hamer Road.

On April 18, 2016, Administrative Contract Adjustment 1 to the Agreement was executed providing for an additional 70 calendar days claimed by the Contractor due to inclement weather.

On February 14, 2017, Administrative Contract Adjustment 2 to the Agreement was executed providing for an additional 38 calendar days claimed by the Contractor due to inclement weather.

On March 30, 2017, Administrative Contract Adjustment 3 to the Agreement was executed providing for an additional 9 calendar days claimed by the Contractor due to inclement weather.

At its meeting on May 9, 2017, the Board of County Commissioners executed Change Order 1 to the Agreement providing for an additional $696,999.44 for the installation of new signalization at the intersections of Fort Hamer Road/Golf Course Road and Fort Hamer Road/ Mulholland Road; and an additional 121 calendar days to the construction schedule for work required at Fort Hamer Bridge piers 7, 8, and 14 due to subsurface conditions that differed from the soil borings.

At its meeting on July 25, 2017, the Board of County Commissioners executed Change Order 2 providing for an additional $126,787.95 for the additional asphaltic concrete required to provide proper roadway cross slope drainage for the Upper Manatee River Road portion of the project.



County Attorney Review
Not Reviewed (No apparent legal issues)

Explanation of Other


Reviewing Attorney
N/A

Instructions to Board Records

Original to Board Records

Copies to:

Johnson Bros. Corporation, 5476 Lithia Pinecrest Road, Lithia, FL 33765 (twinn@johnson-bros.com)

Johnnie Yetter (johnnie.yetter@mymanatee.org), Public Works Department

Towanda Brinson, (towanda.brinson@manateeclerk.com), Accounts Payable Finance Department

Chris Daley (chris.daley@mymanatee.org), Procurement Division



Cost and Funds Source Account Number and Name
The funding sources for this Agreement are Transportation Bonds, Road Impact Fees, and Gas Taxes - Various Accounts in projects 6035560, 6054764, 6082660

Amount and Frequency of Recurring Costs
N/A


Attachment:  14-3257CD Departmental Memo for CO #3.pdf
Attachment:  14-3257CD Johnson Bros Corporation Contract-CO#3.pdf